Jilin Tonghua Steel Bridge Project
Place of use: Tonghua, Jilin
Form of cooperation: lease, installation, technical service, maintenance
Type: 33M three-row single-layer reinforced double-beam beam steel bridge
Features: The steel bridge is guided and supervised by the National University of Defense Technology throughout the installation. It can meet the load of 80T construction vehicles. Due to the requirements of the construction site, the Bailey beam combined bridge pier is used, which is easy to install and dismantle, and has good stability. Installed by the push method, the installation period is 20 days, and it opened to traffic on May 25, 2011.