Changsha Rail Transit Line 2
Construction Unit: China Railway Fifth Bureau
Place of Use: Xiangjiang Middle Road, Changsha
Form of Cooperation: sales installation
Steel Bridge Model: 27m*24m reinforced 6 (lane) + 2 (non-motorized lane) through-type steel bridge.
Features:
The installation period of this steel bridge is particularly tight. Our company carefully arranged and organized it reasonably to complete the installation task on time. It is installed by using the lifting method, the installation period is 12 days, and it was opened to traffic on November 15, 2010 after passing the test by the professional testing agency of Central South University.